水力发电学报 ›› 2015, Vol. 34 ›› Issue (8): 44-51.doi: 10.11660/slfdxb.20150806
• 水力发电 • 上一篇 下一篇
出版日期:
发布日期:
Online:
Published:
Abstract: With continuous development of hydropower on the Wu River, the regulating functions of its upstream reservoirs show great impacts on the hydrological environment and flood defense of a downstream reservoir. This paper develops mathematical models for this river and demonstrates their applications to simulation of the hydrodynamics that are influenced by the scheduling conditions of upstream reservoirs, focusing on influences of joint scheduling on the runoff and storage capacity of the Dongfeng reservoir. The results show that: 1) the inflow of Dongfeng is affected by the operation of upstream reservoirs and its seasonal variations are reduced, with the annual mean high-low inflow ratio decreasing from 5.75 to 4.22 when the upstream Yinzidu operates and further up to 1.96 when both Yinzidu and Hongjiadu are jointly operated and scheduled. 2) The pressure of flood control on Dongfeng can be relieved by running the upstream reservoirs. Its capacity increases by 14.4% and 38.7% in the above two cases respectively. Furthermore, the hydrological environment of Dongfeng can be improved by joint operation of the two cascade reservoirs upstream, thus playing a better role in flood control and power generation.
王晓,逄勇,牛勇,韦雨婷. 乌江上游电站联合运行对东风库区水文情势影响分析[J]. 水力发电学报, 2015, 34(8): 44-51.
WANG Xiao, PANG Yong, NIU Yong, WEI Yuting. Influence of joint scheduling of Wu River’s upstream reservoirs on hydrological regime of downstream Dongfeng Reservoir[J]. JOURNAL OF HYDROELECTRIC ENGINEERING, 2015, 34(8): 44-51.
0 / / 推荐
导出引用管理器 EndNote|Reference Manager|ProCite|BibTeX|RefWorks
链接本文: http://www.slfdxb.cn/CN/ 10.11660/slfdxb.20150806
http://www.slfdxb.cn/CN/Y2015/V34/I8/44
Cited