Abstract: Schedule compression is commonly needed in construction management. Currently, a wide range of methods for schedule compression have been developed in the literature. Almost all these methods consider only cost in the process of determining optimal sequence for activities. But in fact, other factors beyond cost in schedule compression, such as resource availability, risk, and complexity, should have been attributed to the limited use of existing methods. This paper presents a new method for schedule compression of construction projects using an analytical hierarchy process (AHP). This method adopts a multi-objective decision environment in which activities are queued for crashing based on the preferred coefficient calculated by considering resource, risk, and cost. Finally, an example is analyzed to demonstrate the specific optimization procedure. In comparison with the traditional methods, a more objective, comprehensive and accurate preferred coefficient can be achieved, which gives decision makers better optimization solutions to meet the actual needs.
王仁超,陈建友,田 钰. 一种基于AHP的网络计划工期优化方法[J]. 水力发电学报, 2015, 34(2): 199-206.
WANG Renchao, CHEN Jianyou, et al. AHP-based schedule compression method for network planning[J]. JOURNAL OF HYDROELECTRIC ENGINEERING, 2015, 34(2): 199-206.
0 / / 推荐
导出引用管理器 EndNote|Reference Manager|ProCite|BibTeX|RefWorks
链接本文: http://www.slfdxb.cn/CN/
http://www.slfdxb.cn/CN/Y2015/V34/I2/199
Cited