水力发电学报
            首 页   |   期刊介绍   |   编委会   |   投稿须知   |   下载中心   |   联系我们   |   学术规范   |   编辑部公告   |   English

水力发电学报 ›› 2018, Vol. 37 ›› Issue (1): 94-100.doi: 10.11660/slfdxb.20180111

• 当期目录 • 上一篇    下一篇

贯流式机组运行稳定域探讨

  

  • 出版日期:2018-01-25 发布日期:2018-01-25

An analysis on stability domains of tubular turbine units

  • Online:2018-01-25 Published:2018-01-25

摘要: 随着低水头水力资源的开发,贯流式机组占我国水电机组的比重逐步上升,由于该类型机组适用条件和结构的限制,其水流惯性时间常数较大,机组惯性时间常数较小,机组惯性时间常数与惯性比率已远超出我国现行水轮机调节系统相关标准规定的范围。为此,通过分析比较国内外水轮机调节系统标准中被控对象适用条件,调研统计我国现有典型电站的参数及运行状况,并在建立的水轮机调节系统的数学模型基础上分析了该类机组的稳定域与调节品质,表明该类机组具有较大的稳定域,能够安全稳定运行,只要合理整定调节参数能够获得较好的调节品质,且调节参数整定范围也在IEC推荐的常用范围之内,建议对现行国标中惯性比率的要求改为不大于1.5,反击式机组惯性时间常数的要求改为不小于1.5 s。

Abstract: As more low-head hydro resource is developed, the proportion of tubular turbine units in China is gradually increasing. But for all these units, their inertia time constants and inertia ratios usually fall far beyond the required scope of control systems by the current national standard of hydro turbines due to the limits of their application conditions and structures, particularly their overlarge constants of water inertia time and too small constants of unit inertia time. This paper compares the application conditions of the hydro turbine control systems specified in the domestic and overseas standards, analyzes our survey data on the parameters and operation conditions of the existing typical power plants in China, and examines the stable domain and regulation quality using a mathematical model of hydro turbine control systems. The results show that all these existing low-head tubular turbine units still have large stability domains and can operate under safe and reliable conditions. We can demonstrate that better regulation quality can be obtained as long as the control parameters are adjusted properly, and that the required tuning of turbine unit parameters stays within the normal ranges recommended by IEC. Thus we suggest that the requirement of the unit inertia ratio in the standard be revised to be no more than 1.5 and the requirement of the unit inertia time constant no less than 1.5 sec.

京ICP备13015787号-3
版权所有 © 2013《水力发电学报》编辑部
编辑部地址:中国北京清华大学水电工程系 邮政编码:100084 电话:010-62783813
本系统由北京玛格泰克科技发展有限公司设计开发  技术支持:support@magtech.com.cn